Step1: unpacking, system checkup, cleaning
Step2: floor marking for basic machine installation
Step3: installation and system level fine turning,
Step4: electric power, CDA gas, cooling water available.
Step5: system hook-up,
Step6: power on the system and start to checkup each individual component function separately.
Especially laser source status checkup, controller, safety devices, PLC, optic mirrors , etc
Step7: due to the original glass exchange unit is not available anymore, some changes must have to be done at the safety interlock and PLC infeed and outfeed signal bypass
Step7: when we pasted the basic function test of the scribing machine, then we can start the phase No.2, set the machine to handling the bigger substrate.
(a). mechanical checkup: no collision if we modified the system to scribing 1100mm*1400mm
(b). STDMMI configuration
( c) camera calibration and teaching
(d) beam alignment
(e) load a substrate and test running